Last summer, the bulldozers tore up the turf behind La Sierra Community Center, and Engle Road's big green field turned brown. Football and baseball games moved elsewhere. According to the Carmichael Times, July 4 celebrations "fizzled without community fireworks." The 7.8-acre field stayed fenced for more than a year before a ribbon cutting on August 21, 2026. Even then, the grass wasn't open to the general public.
That last detail explains more than it seems to. Four years after Carmichael voters approved Measure G, the renovations it paid for are now coming back one by one. The ones that finished late all got stuck at the same point. Concrete is poured, fencing is up, and the park sits waiting on a shipment or on new grass to root. If you know which of those a fenced park near you is waiting on, its posted estimate makes a lot more sense.
Where the money came from
Measure G passed on November 8, 2022. Ballotpedia's transcription of the certified results shows 67.59% yes, or 11,168 votes against 5,356. It authorizes up to $31.9 million in general obligation bonds for the Carmichael Recreation and Park District. The 2022 ballot materials estimated the levy at $19 per $100,000 of assessed value.
The district sells the bonds in series, so the work comes in waves instead of all at once. CRPD's February 2023 update called for three issues of about $10 million each, with roughly three years to spend one series before selling the next. CRPD also says bond money goes only to deferred maintenance and new projects, never to staff positions, and a Bond Oversight Committee reviews project spending.
Those waves are why 2026 has felt crowded. Late Series I sites and early Series II sites were all under construction in the same spring.
What's open, what's fenced
As of CRPD's September 2026 project updates, here is where each site stands.
| Park | What changed | Status |
|---|---|---|
| Glancy Oaks Park | New playground and surface, accessible entry at the southwest corner | Completed January 2026 |
| Carmichael Park, Phase I | New playground near the Veterans Memorial Building, new restroom near the tennis courts, two tennis courts converted to six pickleball courts | Completed April 2026 |
| O'Donnell Heritage Park | Accessible walkway around the park, restored butterfly garden and entrance, resurfaced basketball court | Completed August 14, 2026 |
| La Sierra Community Center field | About 331,000 sq ft of natural grass, new irrigation and drainage, walking path, T-ball infields, bleachers | Complete; permitted use only |
| Jan Park | North-side paths, bottle-filler fountain with dog bowl, misting stick, enclosed toddler swing | Under construction; estimated end of October |
| Cardinal Oaks Park | New playground, pedestrian lighting, accessibility work, new south parking lot | Closed; estimated Late Fall 2026 |
O'Donnell Heritage Park finished on schedule. In April, CRPD said Lister Construction would build from May through August, and the ribbon cutting happened on August 14. Even there, the July update was still waiting on a delivery of bollards.
Grass sets its own schedule
The La Sierra field shows the first kind of wait. In December 2025, the concrete paths were finished, but weather pushed back the sod, and the delays continued through January and February. The sod went down in pieces across April and May as spring storms came through, and CRPD said the field would need about 90 days to grow strong roots before regular use.
Ninety days from late May puts you right around the August ribbon cutting. In August, permitted use began, but the field stayed closed to general public use "to allow breaks in use for the grass to recover and continue to establish." CRPD maintenance staff took over field care that month. In September, the district called the project complete and said it was still working with the contractor on adjustments and repairs during the maintenance period.
The Carmichael Times put the field's combined cost at more than $1.7 million, all paid by Measure G, along with half a mile of new walkways and rebuilt entrance gates. Carmichael Little League and Capital Valley Youth Soccer League are among the groups based at the center. To book time on the field, submit CRPD's field rental inquiry with the dates and times you need.
Equipment sets the other schedule
Jan Park, at 4310 Jan Drive, shows the second kind of wait. Here is how its estimated finish has moved:
- April 2026: Parker Landscape Development set to build from the end of April through June.
- June and July 2026: Concrete poured and finished. The contractor left the site until all "long-lead equipment" arrived.
- August 2026: Crews back on site, with completion estimated for the end of September.
- September 2026: North-side flatwork in progress, another concrete path to be excavated, the enclosed toddler swing about to be installed, and completion "likely" by the end of October.
The concrete was done by July. The four months since went to waiting on equipment and then adding the pieces that came with it. A fenced park with its concrete already poured may be closer to finished, or further from it, than it looks. It depends on what's still sitting on a truck somewhere.
Cardinal Oaks still has a delivery on its calendar
Cardinal Oaks Park, on El Camino Avenue near Garfield Avenue, is the biggest of this year's projects still closed. Its posted estimates have moved more than once. In April, CRPD expected Xeela Engineering to build from late May through late September. In May, the estimate was the end of October, with a full park closure starting May 28 that was planned to last until the beginning of August. The current estimate is Late Fall 2026. CRPD's main Measure G overview page still shows the original May-to-September window. Trust the dedicated project page over the overview.
The September update shows where things stood. The playground was being installed, the parking lot and concrete walkways were set for mid-September, and the pour-in-place rubber surfacing was planned for the end of the month. In August, CRPD said the new light poles were expected in late October. That puts a delivery on this park's calendar after the playground work, and pedestrian lighting is part of the project's scope. In June, the Carmichael Times expected an October reopening. As of this writing, early October, there's no CRPD update newer than September, and no specific reopening date has been posted.
The next round, and what's open now
Carmichael Park's second phase covers accessibility and safety upgrades to parking lots, drive aisles and walkways at 5750 Grant Avenue. As of September, the plans were still under Sacramento County review, with no construction start posted. Further out, CRPD's planned Series III list includes:
- Bird Track Park: new playground and rubberized surface
- Patriots Park: new playground, walkway improvements, pedestrian security lighting
- Del Campo Park: soccer field turf repair, a new restroom by the soccer field, parking lot work, a creek bridge
- Sutter-Jensen Community Park: decomposed granite on the community garden paths, parking lot improvements
- Carmichael Park: accessibility improvements at Veterans Memorial Hall
CRPD notes on the same page that "this schedule may change." Del Campo's turf repair is the item to keep an eye on, because it depends on grass establishing, the same thing that kept La Sierra's field partly closed this summer.
In the meantime, Carmichael Park's finished Phase I upgrades will get plenty of use this month. The Founder's Harvest Festival runs October 10 from 10 a.m. to 2 p.m., with free admission, food trucks, a pumpkin patch, a petting zoo and a car show. Barktoberfest follows on October 17 from 10 a.m. to 1 p.m., with a pet costume contest and adoptions. Both take place at the park where two tennis courts became six pickleball courts this spring, next to the new restroom by the courts.
At Caviard Realty Associates, Pierre keeps up with neighborhood projects like these, including which park is next on CRPD's list and when the fences are expected to come down. If you'd like to know how the upcoming Measure G work lines up with your street in Carmichael, request a neighborhood consultation with Pierre.